Warehouse Electrical Installation: What to Plan Before Automation Equipment Arrives

Taking on a new warehouse? Expanding an existing distribution centre? Installing conveyors, AutoStore, AS/RS or another automated handling system?

A successful warehouse electrical installation needs to be considered much earlier than many project teams realise.

Modern warehouses rely on far more than lighting and general power. Automated equipment can introduce substantial new electrical loads, additional distribution, containment, controls, communications, safety systems and commissioning requirements.

If those elements are not planned alongside the automation package, electrical work can quickly become a bottleneck later in the project.

Whether you are a warehouse operator, 3PL, ecommerce business, main contractor or automation integrator, here are the key things to consider before installation begins.

warehouse electrical installation

What does a warehouse electrical installation include?

A warehouse electrical installation can cover everything from the building’s main power distribution through to the final electrical connections for automation equipment.

The exact scope will depend on the facility, but a modern distribution or fulfilment centre may need LV power distribution, new distribution boards, cable containment, small power, warehouse and emergency lighting, conveyor supplies, motors and drives, control panels, PLC and field wiring, sensors and scanners, safety circuits, robot charging infrastructure, packing and workstation supplies, data and communications, plus testing and commissioning support.

The important point is that these systems cannot always be designed in isolation.

The warehouse electrical installation needs to work with the automation design, mechanical installation, controls, building layout and commissioning programme.

When should you involve a warehouse electrical contractor?

Ideally, before the automation equipment arrives on site.

Better still, involve your electrical contractor while layouts, loads and installation programmes are still being agreed.

That gives the project team time to confirm whether enough electrical capacity is available, where new equipment will be supplied from, whether additional distribution boards are required, where containment needs to run and who is responsible for each connection. It also helps identify what must be completed before conveyors or steelwork restrict access, which areas need to remain operational and when the electrical installation has to be ready for commissioning.

These questions become far harder, and often more expensive, to solve after equipment is already being installed.

How do you know if your warehouse has enough electrical capacity?

One of the first things to establish is whether the existing electrical infrastructure can support the proposed equipment.

A warehouse that has previously operated with conventional racking and manual picking may have very different electrical requirements once automation is introduced.

Additional demand can come from conveyor and sortation systems, automated storage, robot chargers, automated packing machinery, picking stations, AS/RS cranes, control panels, drives, IT infrastructure, extra HVAC and new mezzanine areas. Even when each load looks manageable on its own, the combined demand can change what is required from the building electrical infrastructure.

An electrical assessment can identify whether the existing distribution has sufficient capacity or whether upgrades are required.

It is also worth looking beyond the immediate project. If the business expects to add another conveyor line, extend the AutoStore grid or increase robot numbers later, allowing for future capacity during the first phase can avoid having to redesign the electrical infrastructure again.

Planning electrical installation for conveyor systems

Conveyors are a major part of many warehouse automation projects, but the electrical work behind them can be extensive.

A conveyor electrical installation can involve main and local power supplies, containment along conveyor routes, motor connections, drives and VFDs, control-panel connections, PLC I/O, sensors, barcode scanners, diverters, emergency-stop circuits, safety devices and network cabling. Testing and commissioning then need to be coordinated with the wider controls and mechanical programme.

The installation also needs to follow the mechanical programme. If containment or cabling is installed at the wrong point in the sequence, access can become difficult once conveyor steelwork, guarding or mezzanines are in place.

Good coordination between the electrical contractor, conveyor supplier and controls engineers can prevent those clashes.

Hills Electrical Group has delivered electrical systems supporting large automated conveyor installations, including warehouse projects involving thousands of metres of conveyor, multiple control panels and complex automated handling systems.

What electrical infrastructure does AutoStore need?

AutoStore projects have their own electrical requirements.

Depending on the system design, the electrical scope can include robot chargers, carousel and conveyor ports, controllers, picking stations, distribution boards, network equipment, wireless access points, conveyor interfaces, mezzanine areas, lighting and additional workstations.

The timing of the work is particularly important. Some electrical infrastructure may need to be installed before the grid, steelwork or surrounding automation restricts access.

On a recent apparel fulfilment project, Hills delivered electrical infrastructure supporting a new AutoStore system including carousel ports, conveyor ports, robot charging points, distribution boards, mezzanine power, wireless access points and LED lighting.

That type of project demonstrates why AutoStore electrical work should be planned as part of the wider automation programme rather than treated as a standard electrical fit-out.

What about AS/RS and automated storage systems?

Automated Storage and Retrieval Systems can create significant electrical requirements.

The exact requirements depend on the technology. Stacker cranes can need dedicated power, control systems, communications and safety circuits, while shuttle systems may add charging infrastructure, distribution, controls and network connections.

Automated picking systems can add conveyor interfaces, scanners, controls and safety systems. Robotics and AMRs can introduce charging stations, communications infrastructure and further integration with surrounding equipment.

The electrical contractor needs to understand not just the individual pieces of equipment, but how the wider system fits together. In a modern distribution centre, conveyors, cranes, robots, control systems and software are all parts of the same operation.

Are you fitting out a new warehouse?

A newly leased warehouse can look almost ready to occupy while still requiring significant electrical work before an automated operation can move in.

Typical changes can include new distribution boards and circuits, revised containment routes, power for conveyors and automation, mezzanine power and lighting, packing areas, charging infrastructure, control panels, data cabling, emergency-lighting alterations and additional small power. All of this then needs to be tested and certified before handover.

If you have recently signed a warehouse lease, appointed an automation integrator or agreed the facility layout, that is a good point to review the electrical scope.

Waiting until the machinery arrives can limit your options and put unnecessary pressure on the installation programme.

Can warehouse electrical work be completed while the building remains operational?

Yes, but it requires more planning.

A large proportion of warehouse automation work involves existing buildings rather than completely new facilities.

A live-site project might involve expanding capacity, adding new conveyors, introducing AutoStore, replacing legacy equipment, creating a new packing area, installing automation in phases or reconfiguring an existing distribution centre.

In a live warehouse, the electrical programme may need to work around shifts, peak trading, planned shutdowns and existing equipment.

Important considerations include isolation windows, temporary supplies, installation sequencing and commissioning. The earlier this is discussed, the easier it is to build a workable programme.

Who is responsible for the electrical package on an automation project?

This varies considerably between projects.

The electrical package might be procured directly by the warehouse operator, retailer or 3PL, or it may sit with the automation integrator, conveyor supplier, main contractor or M&E contractor. The route varies from project to project, which is why scope boundaries need to be agreed early.

Before installation starts, everyone should understand who supplies the control panels, installs containment, supplies field cabling, terminates equipment, provides distribution boards, installs safety circuits, provides data infrastructure, tests the installation and supports commissioning.

Unclear scope boundaries are one of the easiest ways for gaps to appear. Something that everybody thought was included can suddenly become an urgent variation once the system reaches commissioning.

What should you check before warehouse electrical installation begins?

Before mobilisation, we recommend checking six things:

  1. Load and capacity: Confirm the proposed loads for all new equipment and whether the existing electrical infrastructure can support them.
  2. Layout and distribution: Fix the position of conveyors, ports, chargers, workstations and control panels, then agree where equipment will be supplied from and whether new distribution boards are needed.
  3. Containment and sequence: Plan cable routes early enough that containment can be installed before mechanical equipment, steelwork or mezzanines restrict access.
  4. Controls, safety and data: Agree responsibility for PLCs, field wiring, safety interfaces, emergency stops, network infrastructure and equipment connections.
  5. Programme and live operations: Identify what must be electrically complete before testing and commissioning, and how shutdowns or live-site restrictions will be managed.
  6. Scope and future expansion: Make responsibilities clear between contractors and decide whether spare capacity or containment should be allowed for future phases.

Choosing warehouse electrical contractors

A warehouse automation project requires more than general commercial electrical experience.

Your electrical contractor should be comfortable working alongside automation integrators, conveyor suppliers, controls engineers, PLC engineers, main contractors, warehouse operators, project managers and commissioning teams.

They also need to understand the programme pressures that come with logistics projects. A new distribution centre may have a fixed opening date. An ecommerce warehouse may need to be ready before peak. A live facility may only allow shutdowns during evenings or weekends.

The electrical installation needs to fit that reality.

When choosing a contractor, ask for examples of comparable warehouse and automation work rather than simply general industrial projects.

Warehouse automation works best when the electrical package is planned early

The electrical installation is the infrastructure that allows the automation system to operate.

Power, controls, communications, containment and safety systems all need to be in the right place at the right time.

If you are planning a new warehouse, distribution-centre fit-out, warehouse extension, conveyor system, AutoStore, AS/RS, automated picking, robotic handling, sortation or automated packing, bring the electrical team into the project before installation begins.

It gives everybody more time to identify capacity issues, coordinate equipment and agree responsibilities before they become problems on site.

Planning a warehouse electrical installation?

Hills Electrical Group supports warehouse operators, retailers, ecommerce businesses, 3PLs, main contractors and automation integrators with electrical installation for automated warehouse and distribution-centre projects.

Our experience includes power distribution, containment, conveyor electrical installation, control systems, AutoStore infrastructure, robotics, field wiring, data, testing and commissioning support.

If you are planning a new warehouse, expanding an existing facility or installing warehouse automation, speak to our team about the electrical requirements early in the project.

Get in touch today by calling 01384 671660 or email info@hillsgroupuk.com

Follow us on LinkedIn for regular updates.

 

FAQs

What does a warehouse electrical installation include?

A warehouse electrical installation can include power distribution, distribution boards, lighting, containment, conveyor supplies, control panels, machinery connections, safety circuits, charging infrastructure, data cabling, testing and commissioning.

When should I appoint a warehouse electrical contractor?

Ideally during the planning or design stage. Early involvement allows the electrical contractor to check power capacity, identify distribution requirements, plan containment routes and coordinate the electrical work with automation and mechanical installation.

Do automated warehouses need more electrical capacity?

Often, yes. Conveyors, robotics, AS/RS, AutoStore, charging infrastructure and automated packing equipment can all increase electrical demand. The existing installation should be assessed before equipment is specified or installed.

What electrical work is required for warehouse conveyors?

Typical work can include containment, motor and drive supplies, control-panel connections, sensors, scanners, field wiring, safety circuits, emergency stops, network connections and commissioning.

Does AutoStore need specialist electrical infrastructure?

AutoStore installations can require electrical infrastructure for robot chargers, ports, controllers, conveyors, workstations, distribution boards, data networks, mezzanines and lighting. The electrical work needs to be coordinated with the system layout and installation sequence.

Can electrical work be carried out in an operational warehouse?

Yes. Warehouse electrical work can often be phased around live operations, shifts and planned shutdowns. The programme and isolation requirements should be agreed before work begins.

Who normally appoints the electrical contractor on a warehouse automation project?

It varies. The electrical contractor may be appointed by the warehouse operator, retailer, 3PL, automation integrator, main contractor or M&E contractor. Clear scope boundaries are important so there are no gaps between packages.

 